Burkhalter Road Data Center (4AM Development)
4AM Development, LLC (developer; operator undisclosed) · Statesboro, GA · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 6539 Burkhalter Road
- Coordinates
- 32.4049295, -81.7440222
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Statesboro City Council approved the rezoning of the ~27-acre Burkhalter Road site 3-2, with the mayor breaking the tie. A special use permit is still required and no operator has been selected.
Underlying source
Source notes
Two-story building of roughly 230,000 sq ft plus a 3/4-acre reserved Georgia Power substation site. The concept plan describes 40-90 MW and the developers applied to Georgia Power for a maximum of 99 MW; no single figure is asserted here. Owners named as Bobby Bagwell and Charles C. Way; the site is being zoned speculatively. No investment figure is recorded. The Statesboro Herald reports a developer-funded fiscal-impact analysis by Economic Impact Group LLC for the Development Authority of Bulloch County that "suggested a $1.2 billion total 10-year investment", under the subheading "Supposed $1.2B project"; developer Way said private investment would depend on the ultimate design but would be "somewhere in the high hundreds of millions of dollars". Coordinates are approximate to Burkhalter Road pending parcel confirmation.
Sources and provenance
- Mayor and council approve rezoning for Burkhalter data center by 3-2 vote · source retrieved 2026-09-12
- Eleven citizens and nonprofit group file legal challenge to Statesboro data center rezoning · source retrieved 2026-09-23
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.