SOURCE-LINKED U.S. REGISTRY

Shippingport Industrial Park

Aligned Data Centers · Shippingport, PA · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
40.63, -80.44
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
2000 MW
Source record updated
2026-10-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Underlying source
  2. Permitted

    Conditional use granted. Data Center Dynamics reported on February 3, 2026 that the Shippingport Borough council had held a public hearing the week before on Aligned's conditional use requests and approved the use permit, and that council documents suggest the proposed campus is known as Project Phoenix.

    Underlying source
  3. Under construction

    Aligned Data Centers broke ground on the 2 GW 'Project Phoenix' campus in Shippingport on September 10, 2026, moving the site from permitted to under construction.

    Underlying source

Source notes

Aligned's Project Phoenix campus in the Shippingport Industrial Park, a former coal-plant site. Aligned's press release of September 10, 2026 describes a 2 GW campus spanning three facilities and announces the groundbreaking that day. Data Center Dynamics reported in February 2026 that Aligned was then planning two natural-gas-powered buildings within the 660-acre industrial park, with construction possibly starting later in 2026. The 660 acres is the size Data Center Dynamics gives for the whole industrial park, not a campus figure, so no land area is recorded; Marcellus Drilling News reports Aligned bought 650 acres from Frontier Group of Companies in July 2026 for $223 million.

Aligned's press release of September 10, 2026 says the campus will use its own dedicated onsite power source rather than the local electrical grid, next to the Shippingport Power Station, a former coal plant being redeveloped as a natural gas energy campus, and expects excess power to flow back to the grid once completed. The release describes a 2 GW campus; the Data Center Dynamics report of February 2026 gives no campus MW figure.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory