Amazon Devlin Technology Park
Amazon Web Services · Bristow, VA · United States
Facility record
- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 38.724, -77.558
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Stanley Martin Homes assembled 270-acre site and applied for rezoning for up to 3.5 million sq ft of data center use
Underlying source - Permitted
County Board approved rezoning; circuit court upheld 2024; Virginia Court of Appeals upheld September 2025. Amazon purchased 188.5 acres (70% of park) from Stanley Martin for $700M on November 5, 2025.
Underlying source
Source notes
$700M land purchase is among the highest ever for undeveloped land in the US. Zoning allows up to 3.5 million sq ft of data center space and three substations. Adjacent to Microsoft's Bristow campus parcel. Coordinates approximate for northwest corner of Devlin and Linton Hall roads.
Sources and provenance
- Amazon buys 189 acres in Prince William tech park for $700M · source retrieved 2026-07-06
- Amazon pays $700M for planned data center site in Virginia's Prince William County · source retrieved 2026-07-06
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.