Ardent Data Centers (Northern Data Group) · McKees Rocks, PA · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 40.4646, -80.081
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- 5 MW
- Planned capacity, source-reported
- 20 MW
- Source record updated
- 2026-09-21
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Operational
Acquisition of the existing Pennsylvania data center completed; conversion to a high-density HPC facility expected complete Q4 2024, scaling to 20 MW.
Underlying source
Source notes
41,000 sq ft building on 7.5 acres in McKees Rocks, Allegheny County, acquired by Ardent (Northern Data Group) in January 2024 with 5 MW in place and a phased path to 20 MW. Purpose-built for GPU/HPC workloads at 135 kW+ rack densities. Street address is reported by third-party directories as 615 McMichael Road but was not confirmed in the sources cited here, so it is omitted.
Sources and provenance
- Ardent Data Centers, a Northern Data Group company, completes acquisition of Pennsylvania data center · source retrieved 2026-09-21
- Data Centers in Pennsylvania — Project List & Locations (HPC data center, Northern Data, Allegheny, 20 MW) · source retrieved 2026-08-17
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.