Atlas Agro Richland Data Center Campus
Atlas Agro North America · Richland, WA · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 2100 Horn Rapids Road
- Coordinates
- 46.36, -119.325
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 320 MW
- Source record updated
- 2026-10-12
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Richland City Council unanimously approved a land-option agreement with Atlas Agro for 275 acres at 2100 Horn Rapids Road, with a $250,000 nonrefundable option fee.
Underlying source
Source notes
Swiss fertilizer developer Atlas Agro offered the City of Richland just under $24 million for 275 acres in the Northwest Advanced Clean Energy Park, adjacent to its planned zero-carbon nitrate fertilizer plant. The campus would comprise five data center buildings of roughly 500,000 sq ft each, with construction targeted to begin in 2027. Columbia Riverkeeper's February 2026 report puts the campus's power requirement at at least 320 MW. Power would come via a Bonneville Power Administration line serving both the data center and the fertilizer plant. Atlas Agro's North American president describes the data center as 'a partner that helps us build the necessary power and utility infrastructure.' Coordinates are an approximate geocode of the stated address.
Project depends on a power line the Bonneville Power Administration plans to build, shared with Atlas Agro's planned fertilizer plant.
Sources and provenance
- Richland OKs option agreement for Atlas Agro data center · source retrieved 2026-10-12
- A Closer Look: Columbia River Data Centers (February 2026) — Benton County, Washington · source retrieved 2026-09-05
- What to know about 4 major data center proposals for Tri-Cities area · source retrieved 2026-09-05
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.