SOURCE-LINKED U.S. REGISTRY

Atlas Compute AI Data Center Campus

Atlas Compute (infrastructure by Penguin Solutions) · Fort Pierce, FL · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Post Office Road, Midway Industrial Park
Coordinates
27.44, -80.33
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
240 MW
Source record updated
2026-10-20

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Land and utilities secured for a 240 MW initial campus, with up to 1 GW expansion capacity.

    Underlying source

Source notes

Land and utilities secured. Targeting operational Q4 2026-Q1 2027. Up to 1 GW expansion capacity. Distinct from the withdrawn Sentinel Grove/Project Jarvis project in the same county.

Atlas Compute plans to build its own natural gas-fired power plant to serve the campus rather than draw the full load from the utility; the site borders FPUA's Treasure Coast Energy Center.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory