Project Springbank (Atlas Development Bartow County Campus)
Atlas Development LLC · Adairsville, GA · United States
Facility record
- Lifecycle
- CancelledSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Barnsley Gardens Road
- Coordinates
- 34.30926, -84.96325
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 432 MW
- Source record updated
- 2026-09-30
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Bartow County submitted Development of Regional Impact #4403 ("Project Springbank", developer Atlas Development LLC) to the Georgia DCA; determined to warrant regional review 2025-02-24.
Underlying source - Cancelled
Atlas Development withdrew rezoning application Z-25-00006 through its attorney on 2025-05-13, the day before the sole commissioner was to rule, after the Bartow County Planning Commission voted 6-1 on 2025-04-28 to recommend denial. Atlas gave no reason. No refiling of this site has been found.
Underlying source
Source notes
Six buildings totaling 2,274,000 sq ft (about 379,000 sq ft each), per DRI #4403, which states the project "will utilize closed loop technology to reduce water and sewer demand." The DRI states a build-out value of $4,500,000,000 and completion in December 2031, and leaves the electrical-load and energy-provider fields blank. The 432 MW figure (six buildings of up to 78 MW each) is from press reporting on the site plan, not the DRI. Property owners per the DRI: The Darryl William Edwards Living Revocable Trust, King Curtis LLC and Riverside NVR LLC. Acreage: the county's minutes and the Daily Tribune give 630 acres for the rezoning request (to Business Park District); earlier press gave 588. Coordinates are the point stated in the DRI filing, not a surveyed site centroid. No named end-user operator was attached to the project. Distinct from Atlas Development's later Stiles Road application off Euharlee Road (withdrawn December 2025).
Sources and provenance
- New data center proposal in Bartow would require as much power as 324K homes · source retrieved 2026-08-28
- Data Center Operator Planning $4.5B Bartow County Campus · source retrieved 2026-09-21
- Springbank data center application withdrawn · source retrieved 2026-09-30
- Bartow County planning commission votes to recommend denying data center rezoning request · source retrieved 2026-09-30
- Development of Regional Impact #4403, Project Springbank — initial form (location, owner, size) · source retrieved 2026-09-30
- Development of Regional Impact #4403, Project Springbank — additional information (value, water, sewer) · source retrieved 2026-09-30
- Petition started, town hall set regarding proposed data center · source retrieved 2026-09-30
- Minutes, Public Meeting, Bartow County Commissioner, May 14, 2025 — Z-25-00006 withdrawn · source retrieved 2026-09-30
- Town hall held, public hearing postponed for proposed data center · source retrieved 2026-09-30
- Backlash over proposed data center near Adairsville · source retrieved 2026-09-30
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.