AWS New Albany (3180 Beech Road)
Amazon Web Services · New Albany, OH · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 40.104129, -82.750939
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Operational
Listed as built 2024 / fully operational by data-center directories; Licking County Auditor land-use class 305 ('Research/Chemical Labs' = built industrial) on the Amazon Data Services Inc parcel.
Underlying source
Source notes
Operational AWS data center on a ~106-acre Amazon Data Services Inc parcel on Beech Rd NW, New Albany — a second built AWS building on Beech Rd, physically distinct from the tracked '2550 Beech Road' building (AWS New Albany (2550 Beech Road), ~1.1 km south) and from the under-construction ~458-acre Beech/Miller five-building expansion (AWS New Albany (Beech/Miller Road Campus)). Data-center directories label it the 'North Hub'; the 112-acre parcel was bought April 2020 for $21.8M and the building is listed as built 2024 / fully operational. Licking County Auditor land-use class 305 ('Research/Chemical Labs' = built industrial, vs class 300 'Industrial Vacant Land' on the neighboring pre-construction parcels); owner Amazon Data Services Inc. No site-specific IT-load MW is disclosed. Coordinates are the Licking County Auditor parcel centroid (parcel 095-111618-04.000).
3180 Beech Rd is part of Amazon's New Albany 'Silicon Heartland' campus expansion (112 acres acquired 2020, adjacent to the original 68-acre campus).
Sources and provenance
- Licking County Auditor parcel/GIS record (parcel 095-111618-04.000, Beech Rd NW — Amazon Data Services Inc, Industrial land-use class 305 'Research/Chemical Labs' = built, 106.4 ac) · source retrieved 2026-07-19
- Amazon 3180 Beech Rd Campus ('North Hub') — fully operational, built 2024; 112-acre parcel bought April 2020 for $21.8M, distinct from the original 2570 Beech campus and the Beech/Miller expansion · source retrieved 2026-07-19
- Amazon: 3180 Beech Rd Campus Data Center (Baxtel) · source retrieved 2026-07-24
- AWS News Blog: More Amazon wind and solar farms are live · source retrieved 2026-07-24
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.