AWS Hayden Run Campus
Amazon Web Services · Hilliard, OH · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 5109-5129 Hayden Run Rd
- Coordinates
- 40.059949, -83.134305
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Operational
First building completed ~2018 (AWS's first Ohio region facility, ground broken 2015) per data-center directories; Franklin County Auditor records the parcel with land-use class 'data center' and 768,498 sq ft of assessed building area (built).
Underlying source
Source notes
AWS's first US East (Ohio) region data center — a ~55-acre Vadata Inc campus at 5109-5129 Hayden Run Rd, Hilliard. Broke ground 2015; first building completed ~2018; a multi-building campus that has continued expanding. Franklin County Auditor land-use class 'data center' with 768,498 sq ft of assessed building area (= built/operational); owner Vadata Inc (Amazon's data-center subsidiary). Data-center directories (DC Byte / baxtel) list several numbered Hayden Run buildings (5109/5113/5117/5121/5125) that correspond to buildings within this single county parcel, not separate sites. No site-specific IT-load MW is disclosed. Coordinates are the Franklin County Auditor parcel centroid. Distinct from the tracked AWS Cosgray Road and AWS Scioto Darby campuses (also Hilliard, Franklin County).
Hayden Run (5109 Hayden Run Rd, Hilliard) is AWS's original Hilliard campus (construction began 2015). The PUCO-approved 73MW Bloom Energy fuel-cell project (228 SOFC units) is confirmed sited at 4120 Scioto Darby Creek Rd — AWS's third, separate Hilliard campus at Scioto Darby Rd/I-270 — not at Hayden Run.
Sources and provenance
- Franklin County Auditor parcel/GIS record (parcel 050-011444, 5109-5129 Hayden Run Rd — VADATA INC, land-use class 'data center', assessed building area 768,498 sq ft = built, 55.2 ac) · source retrieved 2026-07-19
- Amazon Hilliard 5109 Hayden Run — AWS's first US East (Ohio) region data center; broke ground 2015, built ~2018, fully operational, multi-building campus · source retrieved 2026-07-19
- AWS plans third data center campus in Hilliard, Ohio (DCD) · source retrieved 2026-07-24
- Fuel Cells — City of Hilliard · source retrieved 2026-07-24
- Franklin County Auditor GIS: parcel 050-011444, 5109 - 5129 Hayden Run Rd, VADATA INC, class 'data center' · source retrieved 2026-10-14
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.