AWS Hobart Campus

Amazon Web Services · Hobart, IN · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
41.517, -87.263
Serving utility, source-reported
NIPSCO
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Permitted

    Fill permit approved for Hobart Devco prior to public announcement

  2. Proposed

    Amazon publicly announces a $15B NW Indiana investment; Hobart city agreement announced the next day

  3. Permitted

    Hobart Plan Commission approves site plans after majority-opposition testimony

  4. Under construction

    Development begun; spring 2026 groundbreaking confirmed active per press

Source notes

One of AWS's Northwest Indiana campuses (part of a $15B NW Indiana / 2.4 GW umbrella; distinct from Amazon Project Rainier and the separate Wheatfield IN campus). Capacity omitted: the 2.4 GW figure is the NW Indiana total, not Hobart-specific. Investment omitted: $15B is the NW Indiana total, no Hobart-specific figure. Up to 25 buildings ('Hobart Tech Park'), per the mayor's statement to NBC Chicago. As of October 2026 no land area is recorded: the only acreage figure found is a resident's remark quoted by NBC Chicago ("if we think this is going to stop at 725 acres"), not an official or operator figure; shell entities include Hobart Devco, Hobart Owner LLC, TUHAUS LLC/Wylie Capital. ~400 permanent jobs ($37-44/hr) are projections (noted here, not recorded as a jobs figure). $47M upfront community payment is city revenue, not facility capex. Coordinates estimated from 61st Ave/Colorado St. Active litigation: 'No Data Centers Hobart Indiana' sought a TRO on the fill permit (unresolved).

NIPSCO (GenCo, Merrillville); Amazon pays 100% of new power-infrastructure costs under a cost-allocation framework.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.