SOURCE-LINKED U.S. REGISTRY

AWS Mattermeade Tech Campus

Amazon Web Services · Bowling Green, VA · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
38.044, -77.3527
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
770 MW
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Amazon filed for Army Corps permits for the 11-building 'Mattermeade' campus (1,143 acres across Caroline & Spotsylvania counties, SE of I-95 & Mudd Tavern Rd); public comment through March 2025

    Underlying source
  2. Proposed

    Amazon's Spotsylvania rezoning filings describe the 'Orrock Tech Campus', which spans both Spotsylvania and Caroline counties; it is the same campus as this record, not a separate facility, and the 'Mattameade (Spotsylvania)' listing is the same project. The filings give about 1,078 acres and about 4.5 million sq ft in total (the federal permit application gives 1,143 acres): about 920.5 acres in Caroline would hold the data centers, and about 158 acres in Spotsylvania would provide utilities for them. As of October 2026, the outcome of the rezoning request is not recorded here.

    Underlying source

Source notes

1,143 acres across Caroline & Spotsylvania counties, SE of the I-95 / Mudd Tavern Rd interchange; 11 two-story data center buildings plus an office. Amazon is 'seeking to develop a minimum of 770 MW by 2027'. Recorded as proposed (federal permit application filed / public-comment stage as of early 2025). Coordinates are the Bowling Green / Woodford area centroid.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.