SOURCE-LINKED U.S. REGISTRY

AWS Wheatfield Campus (Project Rise)

Amazon Web Services · Wheatfield, IN · United States

Facility record

Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
41.1955, -87.0586
Serving utility, source-reported
NIPSCO
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    AWS presented plans at a public open house at Kankakee Valley High School

  2. Permitted

    Jasper County Commissioners unanimously approved development agreements and a zoning change

Source notes

Codename Project Rise. Nine-building campus on 304 acres of NIPSCO-owned land ~0.5 mi from the R.M. Schahfer Generating Station; part of AWS's $15B Northern Indiana commitment. Capacity omitted: data-center IT load not disclosed; the 400 MW figure is NIPSCO's new gas peaker plant, not the facility's load. DCD reports AWS is 'estimating an investment of around $7 billion'; after the June 17, 2026 county approval, Northwest Indiana Business Magazine reported 'Amazon will invest $7 billion in the community, including $98 million paid in advance.' The record carries the $7 billion figure. Northwest Indiana Business Magazine reported 'The facility is expected to create 250 jobs.' That source does not say the jobs are permanent and the figure is a projection, so no jobs figure is recorded. AWS commits to restore 425 acres of Kankakee River watershed habitat and provide $25M for Wheatfield Township water access; AWS committed $1.25B to offset NIPSCO ratepayer impacts across the broader buildout. Coordinates are the Wheatfield centroid. Distinct from Project Rainier (New Carlisle) and the Hobart IN campus.

Grid power via NIPSCO, which is building a 400 MW gas peaker (target 2027) and a combined-cycle gas plant (target 2029) on adjacent property to serve the campus.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory