Beale Infrastructure Gardner Campus
Beale Infrastructure · Gardner, KS · United States
Facility record
- Lifecycle
- CancelledSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Near the NE corner of 191st Street & South Clare Road, eastern Gardner, KS
- Coordinates
- 38.81, -94.93
- Serving utility, source-reported
- Evergy
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Cancelled
Beale Infrastructure withdrew its application on 2026-05-06 after the City of Gardner said it would grant no incentives; Beale: 'We will not be moving forward with the project at this time.' No revival was found through October 2026.
Underlying source
Source notes
Near 191st St & S Clare Rd. Up to 16 data halls. Distinct from Beale's existing tracked Project Pilot in De Soto, KS. Coordinates are approximate.
New private on-site substation plus a new Evergy substation. Part of a Feb 2026 Evergy 1.9GW electric service agreement batch alongside Google and Meta.
Sources and provenance
- Gardner, Kansas project page · source retrieved 2026-07-09
- KCUR · source retrieved 2026-10-21
- New hyperscale data center could be coming to Johnson County, Kansas · source retrieved 2026-10-04
- Beale: Gardner Campus · source retrieved 2026-10-04
- Beale Infrastructure withdraws application for Gardner data center · source retrieved 2026-10-21
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.