Bitdeer Wenatchee (Pangborn) Data Center
Bitdeer · East Wenatchee, WA · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 624 Urban Industrial Way
- Coordinates
- 47.413902, -120.209264
- Serving utility, source-reported
- PUD No 1 of Douglas County
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 13 MW
- Source record updated
- 2026-10-30
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under constructionUnderlying source
Source notes
Bitdeer's Washington datacenter, referred to as "Pangborn, Washington" in its SEC filings (Pangborn Memorial Airport is in Douglas County, East Wenatchee) and as "Wenatchee, Washington" by aggregators. Originally deployed for Bitcoin mining in May 2018; 13 MW electrical capacity in use as of March 31, 2026. Bitdeer is converting the site to AI cloud use: AI datacenter design documents and building-permit applications submitted, core equipment being delivered, planned to begin with an NVIDIA GB300 cluster; dismantling of the crypto mining datacenter began March 2026 with conversion completion targeted for Q4 2026. Classified as a data center (mid-conversion to AI), consistent with the tracked Bitdeer Knoxville TN conversion. Coordinates approximate (Pangborn area, Douglas County). Distinct from Bitdeer's tracked Ohio (Massillon/Clarington/Niles/Shalersville), Texas (Rockdale) and Tennessee (Knoxville) sites. Public-reception check (2026-09-10): Checked Bitdeer's own SEC 20-F annual report (2026-09-10); it mentions Wenatchee, WA only twice (as a mining-to-AI-datacenter conversion site, and as a single-supplier electricity contract location), with no discussion of community reception, hearings, or local reaction.
Sources and provenance
- Bitdeer Technologies Group FY2025 Form 20-F (filed 2026-04-30) — Item 4.D Property: Pangborn, Washington datacenter, 13 MW, operational May 2018, being converted to AI cloud (GB300 cluster; permits submitted; crypto dismantling began March 2026; target Q4 2026) · source retrieved 2026-07-17
- Data Center Map — Bitdeer Wenatchee, Washington (13 MW) · source retrieved 2026-07-17
- DCD — Bitdeer crypto-to-AI conversion program (Washington among the sites being converted, GB300, Q4 2026) · source retrieved 2026-07-17
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · source retrieved 2026-07-23
- Bitdeer Q2 2026 results press release (Form 6-K Ex. 99.1) · source retrieved 2026-10-30
- Cryptocurrency company applying for AI facility near Pangborn · source retrieved 2026-10-30
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.