Blakely Borough Data Center (withdrawn)
Undisclosed developer (Blakely rezoning applicant) · Blakely, PA · United States
Facility record
- Lifecycle
- CancelledSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 41.4809, -75.5946
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-09-25
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Cancelled
Developers retracted their zoning-change application days before the scheduled hearing, which was then cancelled, amid community opposition. They indicated they would still pursue tree removal and a materials storage pad under existing zoning — a reading the borough manager disputes.
Underlying source
Source notes
Recorded as a withdrawn proposal. The applicant company, acreage and capacity were not disclosed in the cited source, so those fields are omitted rather than estimated. Coordinates are the Blakely borough point; the parcel was not identified publicly.
Sources and provenance
- Blakely Borough data center plans scrapped amid community pushback, Borough responds · source retrieved 2026-09-25
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.