Volo Data Center
Chirisa Technology Parks · Volo, IL · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 300 S Fish Lake Road
- Coordinates
- 42.3486, -88.1382
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.
Source notes
160,000 sq ft leased facility; tenant is CoreWeave, Inc. (public GPU/AI-cloud compute provider) -- every source frames this explicitly as an AI data center supporting AI computing operations. 14 MW is the disclosed power supply (the articles do not name its source), not an IT capacity figure, so no operational capacity is recorded; a planned on-site Bloom Energy fuel-cell/microgrid buildout was targeted for Q3 2025 commissioning but its MW capacity is not disclosed in any source found and is omitted (a distinct figure from the 14 MW supply, not additive to it here). Acreage (~50 acres) and the exact street address/postal code are corroborated only via a single aggregator/cached-search path (Data Center Dynamics coverage of the site's HSBC/Capital One former-tenant history could not be retrieved), so they are single-path and not independently cross-verified; treat address/acreage as approximate. Former site occupant: HSBC (built ~2007), later Capital One (acquired HSBC's US card operations, 2012), vacant and auctioned ~2023 before Chirisa's redevelopment. As of August 2026, no SEC filing or Bloom Energy investor press release had been located to corroborate, and neither is cited as a source. The investment and jobs figures are the commitments listed for Chirisa Volo LLC's 2023 agreement in the Illinois DCEO Data Center Investment Program 2025 Annual Report: a $262,000,000 investment and 20 new jobs.
A 14 MW power supply, source not stated, plus a planned on-site Bloom Energy fuel-cell/microgrid buildout (scheduled for commissioning by the third quarter of 2025 per a July 2024 article; MW not disclosed).
Sources and provenance
- CoreWeave, Chirisa Tap Bloom Energy For Illinois AI Data Center Project · source retrieved 2026-08-02
- Bloom Energy Bringing Fuel Cell Power to CoreWeave Data Center Project · source retrieved 2026-08-02
- Bloom Energy and CoreWeave Partner to Revolutionize AI Data Center Power Solutions · source retrieved 2026-08-02
- Illinois DCEO Data Center Investment Program 2025 Annual Report — Chirisa Volo LLC, Volo, 2023 MOU · source retrieved 2026-10-15
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.