SOURCE-LINKED U.S. REGISTRY

Cloverleaf Troy Data Center Campus

Cloverleaf Infrastructure · Troy, IL · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
38.719, -89.913
Serving utility, source-reported
Ameren Illinois
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    No special-use permit application had been filed as of February 2026; site moved from farmland north of the interstate to farmland off Formosa Road after church-proximity objections.

    Underlying source

Source notes

Four data center buildings plus substation, office and warehouse proposed on farmland off Formosa Road near Collinsville Road. Cloverleaf is a powered-land developer; no end tenant has been named. A permanent-jobs estimate of 100-200 was given as a range and is not recorded as a single value; Cloverleaf's estimate of about 1,000 construction jobs is likewise approximate and not recorded. Coordinates are derived from the mapped road intersection and are approximate.

Developer has requested 500 MW from Ameren, which is studying whether the grid can support the load; Cloverleaf states the data center will pay for all required generation and transmission upgrades.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory