Colovore Reno 1 (RN01)

Colovore · McCarran, NV · United States

Facility record

Lifecycle
OperationalSource-reported lifecycle
Location precision
approximate
Address as listed
100 Italy Drive
Coordinates
39.5341121, -119.4771513
Serving utility, source-reported
Not established
Operational capacity, source-reported
6 MW
Planned capacity, source-reported
Not published
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Permitted

    NDEP Bureau of Air Pollution Control issued a preliminary determination to approve new Class II Air Quality Operating Permit AP7374-5002 (FIN A2675) for the Colovore Reno 1 LLC facility.

    Underlying source
  2. Under construction

    Colovore and King Street announced groundbreaking on RN01 in February 2025, describing the facility as under construction. As of the company's 2026-08-05 abatement filing with the Nevada Governor's Office of Economic Development, Colovore expected to begin operations in Storey County by the fourth quarter of 2026 — construction ongoing, not yet operational.

    Underlying source
  3. Operational

    Colovore announced on 2026-09-09 that it officially opened the first liquid-cooled AI data center on its RNO01 campus in Sparks, NV (6 MW, fully leased); Baxtel lists RNO1 at 100 Italy Dr as operational.

    Underlying source

Source notes

Air permit places the project on the southeast corner of Italy Drive and SR 439, about 2.8 miles south of the I-80/439 interchange, in Section 11, T19N, R22E MDB&M (Air Quality Hydrographic Area 83, Tracy Segment). GOED approved tax abatements in August 2026 (NVBEX reports $4.08M; the GOED board packet gives a 'Total Estimated Tax Abatement over 10 yrs.' of $4,076,970, a ten-year estimate, so no subsidy amount is recorded), against a stated $30 million in capital-equipment investment and 10 jobs at an average $59/hour within five years; the $30M is an equipment figure, not total site capex, so it is not recorded as the investment figure. Colovore's September 9, 2026 announcement gives 6 MW for the first data center on the RNO01 campus, which is recorded as the operational capacity, and says a second data center on the campus is under construction with projected completion in February 2027. Other cited figures differ: Colovore's company profile in the GOED board packet gives '16MW in RNO01', and Baxtel's February 2025 groundbreaking report calls RN01 a 20MW site; neither is recorded.

Five 3,490 kW emergency generators permitted as the only combustion equipment at the site (NDEP Class II minor stationary source).

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.