CoreWeave Digital Crossroads
CoreWeave · Hammond, IN · United States
Facility record
- Lifecycle
- CancelledSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 41.5836, -87.5
- Serving utility, source-reported
- NIPSCO
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 180 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
Hammond approved a 180 MW CoreWeave data center at the Digital Crossroads campus (June 2025); targeted 2027
Underlying source - Cancelled
City of Hammond announced the development agreement expired June 30, 2026 - required milestones and obligations were not completed by the deadline, and no further extensions were offered; no groundbreaking occurred.
Underlying source
Source notes
180 MW facility at the Digital Crossroads campus in Hammond, Lake County; city approved June 2025, NIPSCO lease pending, targeted 2027. Coordinates are the Hammond area centroid. UPDATE (2026-07): the City of Hammond announced the CoreWeave / Decennial development agreement EXPIRED June 30, 2026 - required milestones were not met and no extensions were offered; no groundbreaking occurred. The June 2025 city approval, the 10-year real-property and 20-year personal-property tax abatements, and the ~$2B construction / ~$5B equipment figures were all tied to this now-lapsed agreement (never triggered). Status corrected from under construction to cancelled.
Sources and provenance
- CoreWeave to develop 180MW data center at Digital Crossroads campus in Hammond, Indiana · source retrieved 2026-07-07
- Hammond announces expiration of data center development agreement · source retrieved 2026-07-08
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.