Festus Data Center Campus

CRG (Clayco) · Festus, MO · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
North of Highway 67, west of Highway CC
Coordinates
38.2192, -90.399
Serving utility, source-reported
Ameren Missouri
Operational capacity, source-reported
Not published
Planned capacity, source-reported
600 MW
Source record updated
2026-11-02

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.

Source notes

Festus City Council approved a development-agreement ordinance 6-2 on 2026-03-30 covering a refined ~600MW, four-building conceptual plan on 360 rezoned acres (188 acres permanently preserved). Two active lawsuits seek to invalidate the rezoning/development agreement; no end-user tenant has been publicly named and construction has not started as of August 2026.

Substation pad and Ameren switchyard on site; Tier 4 backup generators.