Festus Data Center Campus
CRG (Clayco) · Festus, MO · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- North of Highway 67, west of Highway CC
- Coordinates
- 38.2192, -90.399
- Serving utility, source-reported
- Ameren Missouri
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 600 MW
- Source record updated
- 2026-11-02
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.
Source notes
Festus City Council approved a development-agreement ordinance 6-2 on 2026-03-30 covering a refined ~600MW, four-building conceptual plan on 360 rezoned acres (188 acres permanently preserved). Two active lawsuits seek to invalidate the rezoning/development agreement; no end-user tenant has been publicly named and construction has not started as of August 2026.
Substation pad and Ameren switchyard on site; Tier 4 backup generators.
Sources and provenance
- Festus council approves $6 billion data center plan despite massive public pushback · source retrieved 2026-08-24
- CRG Unveils Refined Conceptual Design for Proposed Festus Data Center · source retrieved 2026-08-24
- Festus Data Center — community information site · source retrieved 2026-08-24
- Correction source · source retrieved 2026-09-15
- Festus Data Center · source retrieved 2026-11-02
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.