Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
38.8125, -91.1432
Serving utility, source-reported
Ameren Missouri
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Crusoe named as developer at Warrenton Board of Aldermen meeting on November 4, 2025; announcement made by Greater Warren County Economic Development Council consultant.

    Underlying source
  2. Permitted

    Warrenton Planning & Zoning Commission approved conditional use permit and site plan 8-2 on January 8, 2026; Board of Aldermen approved unanimously (two 6-0 votes) on January 20, 2026. Still requires land disturbance review and construction permits before groundbreaking.

    Underlying source

Source notes

Coordinates approximate. Site address: 22151 NW Service Road, Warrenton MO; north of NW Service Road, west of Hwy. W. Two 805,000 sq ft data center buildings + 40,000 sq ft administration building + 621,250 sq ft Ameren-owned switch yard + 603,200 sq ft Crusoe-owned electrical substation. Crusoe described as its 'fifth campus' in its national AI data center portfolio as of June 2026 per the Crusoe newsroom. Meta signed agreement with Crusoe in June 2026 for approximately 1.6GW of AI computing capacity split across Childress TX and Warrenton MO campuses — per-site split not disclosed; confirms Warrenton as AI anchor customer site (MLQ.ai). The conditional use permit and site plan are approved; land disturbance review and construction permits are still outstanding before groundbreaking. Crusoe committed publicly to seek no real property tax or gross receipt tax abatements; would pursue state incentives only (Mid Rivers Newsmagazine). Developer projected annual property taxes of about $80M, with about $44M to local schools (Mid Rivers Newsmagazine). Construction jobs projected at about 2,500 over a three-year build and permanent tech jobs at about 100 (developer estimates reported by Mid Rivers Newsmagazine, not firm contractual commitments). Crusoe historically used on-site flared natural gas but divested those operations; Warrenton campus is grid-connected via Ameren Missouri — no on-site gas generation reported here. Distinct from the Google/Crusoe 'Goodnight' campus in Armstrong County TX.

Ameren Missouri owns and will operate the on-site switch yard; Crusoe owns the on-site electrical substation. Ameren signed confidential large-load agreements totaling 2.2GW with multiple Missouri data centers in February 2026; individual customer details not disclosed (St. Louis Public Radio). No on-site gas generation reported for this campus.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.