CyrusOne OCB1 Council Bluffs Data Center
CyrusOne · Council Bluffs, IA · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- exact
- Address as listed
- 4700 Gifford Road
- Coordinates
- 41.2121526, -95.8779924
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- 9 MW
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Operational
First phase ready for occupancy in 2020.
Underlying source
Source notes
Purpose-built colocation facility. The operator's page describes a 216,000 sq ft data center with 120,000 sq ft of raised floor and, separately, lists 420,000 sq ft of technical IT space; the two area figures are not reconciled. The operator's page lists four 500-ton chillers with CRAH units in each data hall and free cooling below 30°F, and markets the design as "Water-Free Cooling". CRAH units are chilled-water air handlers, so under the methodology's tie-breaker the cooling is recorded as closed-loop even though the chillers reject heat to air. Certified to ISO/IEC 27001, PCI DSS, HIPAA/HITECH, FISMA-High, SSAE 18 Type 2, SOC 2, HITRUST, FFIEC and CSA STAR, and designed to TIA 942 Class 4. The operator's page cites 9 MW of total IT capacity, which is the recorded capacity. A directory lists 18 MW of utility capacity with 6 MW of UPS; those are labelled as utility and UPS capacity rather than IT capacity and are not recorded as capacity.
Sources and provenance
- Council Bluffs, IA: OCB1 — facility specifications · source retrieved 2026-09-21
- CyrusOne Council Bluffs Data Center · source retrieved 2026-09-04
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.