DataBank Project Indo
DataBank · Cartersville, GA · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 34.1651, -84.7996
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 200 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
DataBank filed a DRI for a 200 MW campus on 69 acres at 218 Industrial Park Rd in Cartersville (Bartow County); ~288 MW grid connection; 2032 first phase
Underlying source
Source notes
Project Indo: a 200 MW campus on 69 acres at 218 Industrial Park Rd, Cartersville, Bartow County (~288 MW grid connection filed); DRI submitted, first phase targeted 2032. Coordinates are the Cartersville area centroid. Public-reception check (2026-09-10): Checked a DCD-sourced writeup (2026-09-10, DCD's own page could not be read directly) covering the Development of Regional Impact filing (69 acres, 200MW, $2.4B at full build-out, first phase possibly 2032). No public hearing, resident reaction, or official statement of support/opposition documented in this source.
Sources and provenance
- DataBank files for 200MW data center campus outside Atlanta, Georgia · source retrieved 2026-07-07
- The Daily Tribune (Cartersville, GA) — Data center eyes Cartersville industrial site · source retrieved 2026-07-25
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.