DC OCTO/DDOT Replacement Data Center (60 Florida Avenue NE)
District of Columbia Office of the Chief Technology Officer (OCTO) · Washington, DC · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 60 Florida Avenue NE
- Coordinates
- 38.9102295, -77.0067321
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-20
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.
Source notes
A December 2022 report says the District picked 60 Florida Ave. NE in Eckington in fall 2022 as the building where OCTO/DDOT data center functions moving out of the Reeves Center would be rebuilt. The relocation and decommissioning were budgeted at about $47M; that is a program-wide figure, not this site's investment, so it is not recorded. DGS's 2021 request specified about 500 kW of critical power with N+1 UPS, generators and cooling, which is a requirement and not built capacity. DC permit records show building permit B2306169 (issued 2023-09-21) for an interior renovation of a 2-story commercial building, about 37,000 sq ft, owned by 60 Florida Avenue NE LLC. They also show supplemental electrical, mechanical and plumbing permits from October 2023 through June 2024. None of those permits mentions a data center, so the record stays listed as proposed rather than under construction or operational.
Sources and provenance
- D.C. Issues New RFP For Long-Delayed Reeves Center Remake (Dec 5, 2022) – data center functions to be rebuilt at 60 Florida Ave. NE, Eckington · source retrieved 2026-10-20
- DC DGS Request for Space DGS-RFS-2021-11: OCTO and DDOT Data Center, June 2021 · source retrieved 2026-10-20
- DC Building Permits 2023 – 60 Florida Ave NE (B2306169 interior renovation of 2-story commercial building, approx. 37,000 sq ft, plus supplemental electrical/mechanical/plumbing permits) · source retrieved 2026-10-20
- OpenStreetMap Nominatim geocode for 60 Florida Avenue NE, Washington, DC 20002 · source retrieved 2026-10-20
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.