DC BLOX Atlanta East Hyperscale Data Center Campus
DC BLOX · Conyers, GA · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 33.66, -84.02
- Serving utility, source-reported
- Georgia Power
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 216 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
DC BLOX announced 72-acre land acquisition in Conyers; campus designed for 750,000 sq ft and 216MW at full build-out; hyperscale anchor client named for Phase 1
Underlying source - Under construction
Site preparation underway as of September 2024; Georgia EPD 30-day public comment period on stormwater/wetlands permit (SAS-2024-00075) closed December 18, 2025; non-water-quality construction began December 2025
Underlying source
Source notes
Coordinates approximate; physical address is 1726 Farmer Road NW, Conyers GA 30012. Land: 72 acres acquired per press release; Georgia EPD permit SAS-2024-00075 references 52.84-acre development footprint with three 40MW buildings. Capacity: 216MW total committed by Georgia Power per utility agreement and DRI filing; DC BLOX facility page cites 154 critical/IT MW (1 × 10MW + 3 × 48MW buildings = 154MW IT load). Phase 1 targeted Q4 2025 delivery (hyperscale anchor + 160,000 sq ft available to additional tenants); non-water-quality construction began December 2025; water-quality permitted work may begin October 2026 with full build taking ~1 year. Dark fiber metro ring planned around Atlanta connecting Atlanta East and Atlanta West campuses and continuing to Myrtle Beach cable landing station. AI/ML applications explicitly cited in press materials as key driver of Atlanta hyperscale demand. DISTINCT from DC BLOX Atlanta West campus in Douglas County (Lithia Springs, ~55 acres, 180MW). Investment amount not publicly disclosed. Job counts not disclosed.
216MW committed by Georgia Power; annualized design PUE of 1.3 at full load
Sources and provenance
- DC BLOX announces Rockdale County hyperscale campus (Dec 12 2023) · source retrieved 2026-07-07
- DC BLOX Atlanta East facility page · source retrieved 2026-07-07
- DC Blox files for data center campus outside Atlanta, Georgia · source retrieved 2026-07-07
- EPD launches comment period for proposed Rockdale data campus · source retrieved 2026-07-07
- DC BLOX Rockdale County GA community outreach page · source retrieved 2026-07-07
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.