Decennial Group Akron Data Center
Decennial Group · Akron, IN · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 41.0387819, -86.0282647
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-09-13
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Decennial Group co-founder David Pavlick unveiled early plans at an Akron Banquet Hall open house; no site had been selected and no formal application had been filed with the county.
Underlying source
Source notes
Developer says the project would require roughly 300 acres and $100–150 million of infrastructure improvements (roads, bridges, water system), with an unnamed hyperscale end user. Those are stated requirements, not a secured site or a total project investment, so neither a land area nor an investment figure is asserted. Coordinates are the town of Akron; no parcel has been identified publicly.
Sources and provenance
- Developer unveils data center plan in Akron amid resident concerns · source retrieved 2026-09-13
- Indiana — Data Center Moratoriums (Fulton County, 1 year, enacted 3/3/2026) · source retrieved 2026-09-13
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.