Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
199 Cline Park Court
Coordinates
35.7179, -81.4198
Serving utility, source-reported
Duke Energy
Operational capacity, source-reported
Not published
Planned capacity, source-reported
200 MW
Source record updated
2026-10-15

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    WSOC reports the company bought 21 more acres along US 70 in Hildebran and says the data center would be 200 MW.

    Underlying source

Source notes

The 200 MW figure is the company's own statement as reported by WSOC; The Paper gives no site-specific MW. The parcels are 199 Cline Park Court (19.5 acres, bought 2022) and 0 U.S. 70 E. (21 acres, bought 2026), both registered to Digihost International, Inc. Town and county officials told The Paper the company had not contacted them about permits. The project began as a crypto-mining plan in 2022, and the town then adopted noise and power-use ordinances. Coordinates are an approximate town-level placement.

Baxtel lists the site as adjacent to a high-voltage Duke Energy substation; The Paper describes the newer parcel as near a major Duke Energy substation.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory