ECL CSC-1 FlexGrid AI Data Center
ECL · Santa Clara, CA · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 37.354, -121.955
- Serving utility, source-reported
- Silicon Valley Power (SVP)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 35 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
ECL publicly announced CSC-1, a 35MW FlexGrid-powered AI data center in Santa Clara; first phase delivery targeted Q4 2026
Underlying source
Source notes
Exact street address not publicly disclosed. Coordinates are Santa Clara city centroid (approximate). Announced April 21, 2026. First phase targets Q4 2026 delivery. ECL CEO Yuval Bachar stated the project addresses SVP grid capacity constraints that have forced other data center developers into multi-year interconnection queues. Project targets AI training and inference workloads.
FlexGrid architecture combines SVP on-grid electricity with natural gas and hydrogen fuel cells behind the meter, bypassing SVP grid interconnection queue constraints. Sub-1.15 PUE target. Rack densities 75-270kW for AI high-density compute.
Sources and provenance
- ECL 35MW FlexGrid-Powered Data Center in Santa Clara Builds Atop On-Grid Power for High-Density AI Delivery · source retrieved 2026-07-06
- ECL Plans 35MW Data Center in California That Will Use Some Hydrogen Power · source retrieved 2026-07-06
- ECL Unveils 35MW FlexGrid Data Center in Santa Clara to Tackle AI Power Constraints · source retrieved 2026-09-29
- Hydrogen hustle: ECL taps PowerCell to juice Santa Clara data center · source retrieved 2026-10-19