Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
3356 Clover Valley Rd NW
Coordinates
40.102784, -82.715975
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-15

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    PowerConneX filed the OPSB application (case 26-361-EL-BGN) for the 430 MW New Albany 3 Energy Center, which will serve as primary power for a data center on the same site; OPSB public hearing set for 2026-10-22.

    Underlying source

Source notes

EdgeConneX's second New Albany campus, on the 170.29-acre parcel owned by EdgeConneX MCN New Albany North PropCo 1 LLC (3356 Clover Valley Rd NW; bought for ~$62M in March 2025 per the Columbus Dispatch), north of Rt. 161 between Mink Street and Clover Valley Road, in the Johnstown-Monroe school district. Per OPSB filings as reported by The Reporting Project: about 1.3 million sq ft of data center space in four data halls, plus a substation and energy center; 5.86 acres of isolated wetland and 65 acres of trees would be removed. The co-located PowerConneX New Albany 3 Energy Center (up to ~430 MW of gas generation on ~30 acres; Reporting Project says 450 MW) is on-site generation, not IT load, so it is excluded from the capacity figure. As of October 2026, no data-center IT MW figure was found, so no capacity is recorded. The operator page targets commercial operation of the energy center as early as Q4 2027. Coordinates are the Licking County Auditor parcel centroid (approximate; the parcel is 170 ac). The Census geocoder matched the street address by road-segment interpolation at 40.103464, -82.723486, about 0.6 km west on the road frontage; the parcel centroid was used instead. The 'North Campus' name comes from the EdgeConneX project page URL and title. Distinct from EdgeConneX MCN New Albany (South campus: 9850 Innovation Campus Way, 80 MW Phase I warehouse conversion plus 2x72 MW Phase II, held by the South PropCo 2 / South Opco entities).