Union City Data Center Campus (EdgeConneX / TA Realty)
EdgeConneX (campus investment and operations with TA Realty; land owned by Microsoft, site development by Burr Computer Environments) · Union City, GA · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 33.5870558, -84.5424299
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 324 MW
- Source record updated
- 2026-09-23
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
Phase 1 construction began late 2024; all three phases required to be complete no later than 2032 under the development authority's motion.
Underlying source
Source notes
Three buildings of roughly 612,000 sq ft each (campus over 2 million sq ft) on 136 acres Microsoft bought in April 2024 for $53.5m. Operator is recorded as EdgeConneX rather than Microsoft because the fetched sources describe Microsoft as the landowner while EdgeConneX and TA Realty lead investment and operations — ownership and operation diverge here. Construction employment is reported as a 400–600 range, so only the permanent figure is recorded. Building 1 is designated AT11 by EdgeConneX; this is not Digital Realty's separately tracked ATL11. Coordinates are the Union City centroid (OSM Nominatim); one source lists the mailing address as College Park 30349.
Sources and provenance
- Microsoft: Union City Campus Data Center · source retrieved 2026-09-23
- Details Emerge On Microsoft's $1.8 Billion Investment In Atlanta Data Centers Amid Tax, Development Wrangles · source retrieved 2026-09-23
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.