Equinix Hampton xScale Campus (AT10x–AT13x)

Equinix (xScale) · Hampton, GA · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
33.36499, -84.31697
Serving utility, source-reported
Central Georgia Electric Membership Corporation (CGEMC)
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-14

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Under construction

    Baxtel lists the four-hall campus (AT10x–AT13x) as under construction

    Underlying source

Source notes

Equinix's Aug 6, 2026 release names a Hampton, GA facility served by CGEMC and expects up to $20M/yr in property tax. Baxtel lists four data halls (AT10x–AT13x), coordinates 33.36499,-84.31697, and an under-construction status. Third-party trackers cite 240 MW, which Equinix has not confirmed, so it is omitted here.

20-year take-or-pay style contract. Equinix pays 100% of CGEMC's costs to serve the Hampton facility's contracted demand, including a new high-voltage substation and two new high-voltage transmission lines.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.