- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 39.53, -119.43
- Serving utility, source-reported
- NV Energy
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 400 MW
- Source record updated
- 2026-08-14
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
Groundbreaking attended by Gov. Joe Lombardo at TRIC along USA Parkway.
Underlying source
Source notes
Two adjacent TRIC campuses (South Valley and Peru Ridge) along USA Parkway in Storey County, dual two-story buildings each, ~769-acre combined footprint and a reported combined ~400MW of critical compute plus ~30MW/campus utility power. Fully leased to an unnamed AA-rated, investment-grade tenant (market cap >$3T) under a ~16.4-year triple-net lease; Fleet closed $4.6B in senior secured notes for a 230MW Storey County campus. Groundbreaking May 2026. Coordinates approximate to the TRIC/USA Parkway area.
Fleet filed applications with Nevada state energy regulators on 20 April 2026 for temporary behind-the-meter generation — 144 MW at South Valley and 218 MW at Peru Ridge, about 362 MW combined — using natural gas and diesel engines fed by round-the-clock LNG/CNG deliveries. The plants are intended to run two to three years until NV Energy can scale permanent service to the campuses. Air-quality permit applications were submitted to the Nevada Division of Environmental Protection.
Sources and provenance
- Fleet Data Centers closes $4.6bn in senior secured notes for 230MW Storey County campus · source retrieved 2026-07-30
- Fleet Data Centers breaks ground on 2 facilities · source retrieved 2026-07-30
- Data center firm working on 2 campuses at Tahoe Reno Industrial Center · source retrieved 2026-07-30
- Gov. Lombardo, construction companies break ground on 2 million sq. ft. data center in Storey Co. · source retrieved 2026-07-30
- Why a Northern Nevada data center wants to build its own temporary natural gas power plant · source retrieved 2026-08-14
- Why a Northern Nevada data center wants to build its own temporary natural gas power plant · source retrieved 2026-08-14
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.