SOURCE-LINKED U.S. REGISTRY

Fluidstack Abernathy AI Campus

Fluidstack · Abernathy, TX · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
33.84, -101.84
Serving utility, source-reported
Xcel Energy (SPS)
Operational capacity, source-reported
Not published
Planned capacity, source-reported
168 MW
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Under construction

    TeraWulf developed and then sold the ~120-acre Abernathy campus to Fluidstack in a Google-backed deal; delivery targeted H2 2026

    Underlying source

Source notes

~120-acre campus in Abernathy (Hale/Lubbock counties). Distinct from the separately-tracked Aligned 'Project Caprock' Abernathy campus (313 acres, different operator/parcel). 168 MW critical IT load (240 MW gross). Google-backed via a ~$1.3B lease obligation backstop. The frequently cited $9.5B is 25-year contracted revenue, not capex (in notes only). Note: the Anthropic lease associated with this deal is at TeraWulf's Justified/Hawesville KY campus, not Abernathy. Coordinates are the Abernathy town centroid.

Adjacent Aligned Caprock campus uses Xcel Energy; Fluidstack's Abernathy power provider not named in sources reviewed.