Galaxy Helios Data Center Campus

Galaxy Digital · Afton, TX · United States

Facility record

Lifecycle
OperationalSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
33.72, -100.84
Serving utility, source-reported
Not established
Operational capacity, source-reported
200 MW
Planned capacity, source-reported
1630 MW
Source record updated
2026-10-16

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Operational

    Campus originally built by Argo Blockchain as Bitcoin mining facility (May 2022). Galaxy acquired from Argo in late 2022.

    Underlying source
  2. Under construction

    ERCOT approves additional 830 MW (total 1.6 GW). CoreWeave leases full 800 MW under 15-year agreement worth avg $1B/year. First data hall delivered to CoreWeave in 2026.

    Underlying source
  3. Operational

    Phase I complete: 133MW critical IT load (200MW gross power) delivered to CoreWeave under 15-year leases (two 5-year extension options); rent commencement Q2 2026. Phase II (260MW critical IT load) in development, deliveries expected H1 2027. CoreWeave's total commitment across all phases now 526MW critical IT load. Total approved campus capacity 1.63GW, potential to scale to 3.6GW. Campus now spans 2,200+ acres (expanded from the original 160-acre site).

    Underlying source

Source notes

Built by Argo Blockchain as a ~180 MW Bitcoin-mining facility in 2022; sold to Galaxy Digital in Dec 2022 amid the crypto-market downturn. Galaxy converted the site to AI/HPC hosting for CoreWeave under a 15-year lease signed March 28, 2025. CoreWeave is the anchor tenant using the campus for large-scale AI model training. Phase I (133 MW critical IT load / 200 MW gross) is complete and operational; further phases toward the 1.63 GW approved total remain under construction. Location is near Afton, Dickens County (West Texas). Original site was 160 acres; campus has since expanded to 2,200+ acres across multiple phases. Coordinates are approximate.

ERCOT approved 1.63 GW total; potential to scale to 3.6 GW. $1.4B project financing closed for expansion. Phase I (133MW critical IT load) completed July 2026.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.