Gigaland Data Centers
Gigaland LLC · Remington, VA · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 38.56070838764574, -77.78314256153212
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
proposed per Fauquier County planning staff project database (maintained record of application status)
Underlying source - Proposed
Confirmed: Fauquier County Planning Commission voted 4-1 on June 18 to recommend DENIAL of the original 202-acre, 2.2M sq ft (800MW) application. Rather than proceed to a Board of Supervisors vote on that denied application, the developer WITHDREW the application entirely on Aug 25, 2025 (per FauquierNow). On Aug 20, 2025 Gigaland told FauquierNow it was working on a scaled-down plan of 847,400 sq ft, down from over 2.2 million sq ft; the county said it expects a new application but did not know when.
Underlying source
Source notes
The record is listed as proposed. The original 202-acre application, about 2.2 million sq ft, was withdrawn in August 2025. The Piedmont Environmental Council, an advocacy group, reports a revised application renamed Remington Digital Campus: just over 200 acres, six data center buildings totaling nearly one million square feet. The Fauquier County Planning Commission voted 4-1 on July 16, 2026 to recommend that the Board of Supervisors deny it, and the Board could vote as early as September 2026. As of October 2026, no fetched source states the Board's decision.
Sources and provenance
- Fauquier County planning staff project database (maintained record of application status) · source retrieved 2026-07-17
- Gigaland developers pull Remington data center application; new filing anticipated · source retrieved 2026-07-17
- Fauquier Planning Commission recommends denial of Gigaland data center project in Remington · source retrieved 2026-07-17
- Gigaland: New Packaging, Same Harmful Impacts (with July 20, 2026 update) · source retrieved 2026-10-28
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.