Global AI Windsor Data Center (former Kodak/Carestream campus)
Global AI · Windsor, CO · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 2000 Howard Smith Avenue W
- Coordinates
- 40.4653149, -104.909
- Serving utility, source-reported
- Poudre Valley Rural Electric Association
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 27.5 MW
- Source record updated
- 2026-09-30
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
Construction under way on the former Kodak/Carestream buildings; county has repeatedly ordered work stopped pending zoning approval.
Underlying source
Source notes
Global AI, a New York-based firm, bought a 438-acre former Kodak/Carestream property in unincorporated Weld County near Windsor in November 2025 and is developing a 41-acre data center on it. Phase 1 is stated at 27.5 MW with an ambition to reach 1 GW; no timeline for later phases has been shared. The company says it plans to operate the site alongside Nvidia and Humain. Coordinates are approximate (former Kodak campus, Eastman Park Drive area), not parcel-confirmed.
Poudre Valley REA told the county it can supply only 35 MW until mid-2028, dropping to about 27 MW at the start of 2028 and declining further in 2029, citing limited wholesale supply from Tri-State Generation and Transmission. Global AI's zoning application says later phases would be powered on-site with Bloom solid-oxide fuel cells; no state air permit had been filed as of 2026-07-29.
Sources and provenance
- Weld County officials have told an AI company to stop construction on a new data center. Three times. (read via Internet Archive) · source retrieved 2026-08-26
- AI Data Center Project Information — Town of Windsor · source retrieved 2026-08-26
- Weld County commissioners approve permit for Global AI data center · source retrieved 2026-09-30
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.