Google 5079–5087 Disk Drive Compute Campus (North San José)

Google LLC · San Jose, CA · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
5079 Disk Drive
Coordinates
37.4256515, -121.9639616
Serving utility, source-reported
Pacific Gas and Electric Company
Operational capacity, source-reported
Not published
Planned capacity, source-reported
250 MW
Source record updated
2026-09-21

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Site Development Permit H26-005 submitted 2026-03-06: demolish a ~162,250 sq ft warehouse and build up to three 'research and development' facilities (~482,790 sq ft) with a switching station, substation and 250 MW of on-site electrical capacity; the city classifies it as a large energy-use project, not a data center.

    Underlying source
  2. Proposed

    PG&E's Advice Letter 7785-E (filed 2025-12-18) asks the CPUC to approve energizing 'a new 250 MW data center load' for Google at 5079 Disk Drive, with construction from January 2027 and in-service December 2028; the draft resolution was held again on 2026-09-17 and rescheduled for 2026-10-08.

    Underlying source

Source notes

Classification caveat: Google and the City of San José describe an internal R&D/compute-lab facility, while PG&E's CPUC filing describes it as a 250 MW data center load. Recorded as a data center on the strength of the regulatory filing; Google submitted its interconnection application 2025-03-03.

230 kV transmission-level retail service via a new switching station on the Newark–NRS 230 kV line; CPUC draft resolution would require a refundable advance of $600,000/MW (up to $150M).

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.