Google Data Center (Project Helium)

Google · Sharon, KS · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
37.2486335, -98.4206316
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-21

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Barber County Commission approved (2-0-1) a development agreement with Google for a data center near Sharon, dubbed 'Project Helium'; construction expected to begin early 2027, initial operations targeted for 2030

    Underlying source

Source notes

1.7 million sq ft facility near Sharon, ~8 miles east of Medicine Lodge. County materials estimate roughly $327.5M in total ad valorem tax revenue over 20 years (~$138.4M to Barber County) once the project's Kansas data-center tax exemption period lapses; that is a projected tax-revenue figure, not an investment or subsidy amount, and is not recorded as such here. Construction targeted for early 2027; initial operations 2030.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory