SOURCE-LINKED U.S. REGISTRY

Google West Memphis Data Center Campus

Google · West Memphis, AR · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
35.156, -90.175
Serving utility, source-reported
Entergy Arkansas
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Google (operating via subsidiary Groot LLC) identified as buyer of parcels in West Memphis purchased late 2024

    Underlying source
  2. Under construction

    Official groundbreaking ceremony October 2, 2025; five large-scale data center buildings plus substation and support infrastructure planned

    Underlying source

Source notes

Campus on Bolliger Road, West Memphis. Coordinates approximate for the Bolliger Road industrial area. $4B is Phase 1 through 2027; total planned investment is $10B, which would be the largest private capital investment in Arkansas history. Five data center buildings on 920-acre campus footprint within a 1,178-acre site (per U.S. Army Corps of Engineers filing). A 5,000 construction-jobs figure, unsourced as of July 2026, is not recorded: AEDC states only 'thousands'. The facility draws from Entergy Arkansas, so the energy source is the grid; Arkansas Cypress Solar is a companion renewable project. The site area is 1,178 acres per the Army Corps filing, not 1,200.

Powered by Entergy Arkansas grid supply; Google committed to develop a companion 600 MW Arkansas Cypress Solar project in Jefferson County with 350 MW battery storage to offset energy consumption; Google covering all energy costs; $25M Energy Impact Fund for local efficiency and weatherization

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.