SOURCE-LINKED U.S. REGISTRY

Hut 8 Batavia Data Center

Batavia DC Corp (Hut 8 Corp subsidiary) · Batavia, IL · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
41.859, -88.275
Serving utility, source-reported
ComEd
Operational capacity, source-reported
Not published
Planned capacity, source-reported
50 MW
Source record updated
2026-08-03

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Under construction

    Batavia City Council approved the Master Services Agreement with Batavia DC Corp (Hut 8 subsidiary) 12-1 on July 21, 2025; a follow-up amended agreement (water terms) was approved September 2025. Initial 20 MW operation targeted winter 2026; full 50 MW buildout phased through ~2031.

    Underlying source

Source notes

Requires ~$18M off-site electrical improvements (developer-funded, city-reimbursed over 7 years via utility revenue) and a fourth substation transformer plus added ComEd capacity to reach full 50 MW. City projects ~$2.3M/yr utility revenue + $375K/yr franchise fees at 20 MW, rising to ~$5.7M/$800K at 50 MW.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.