IREN Woods County Campus
IREN (Iris Energy) · Alva, OK · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 36.8031, -98.667
- Serving utility, source-reported
- OG&E
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 1600 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
IREN land bank of ~2,000 acres in Woods County with a secured 1.6 GW power allocation on the SPP grid; power ramp from 2028
Underlying source
Source notes
~2,000-acre land bank near Alva, Woods County, with a secured 1.6 GW power allocation on the Southwest Power Pool grid; initial power ramp scheduled for 2028. IREN's land-bank expansion beyond its operational Texas campuses (Childress, Sweetwater). Single-tracker source → confidence reported. Coordinates are the Alva area centroid. Capacity re-sourced 2026-08-08: IREN's own Oklahoma page states "1,600 MW", "2,000 Acres" and "2028 Substation Energization", status "IN DEVELOPMENT" — replacing an aggregator listing as the basis for the figure. Public-reception check (2026-09-10): Checked baxtel.com's project profile (2026-09-10) -- it covers only technical/permitting facts (2,000-acre site on the SPP grid) plus one unrelated statewide article (Oklahoma's data-center ratepayer-protection bill, 2026-05-16). No hearing, resident reaction, or local-official statement specific to the Woods County/Alva site was found in this source.
Southwest Power Pool (SPP) grid; 1.6 GW allocation.
Sources and provenance
- IREN Woods County Oklahoma · source retrieved 2026-07-07
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · source retrieved 2026-07-23
- IREN Oklahoma data center — 1,600 MW, 2,000 acres, 2028 substation energization · source retrieved 2026-08-08
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.