Iron Mountain Data Centers NJE-1
Iron Mountain · Edison, NJ · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 3003 Woodbridge Avenue
- Coordinates
- 40.5210834, -74.3473835
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- 30 MW
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-09-21
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.
Source notes
TIA-942-certified, 830,000 sq ft on a 43-acre campus, 30 MW with 2N redundancy, N+1 cooling/UPS, ISO 50001/14001 certified, PUE as low as 1.2. Acquired by Iron Mountain in January 2018 as part of a $1.34B acquisition of IO Data Centers' US portfolio (which also included sites in Phoenix, Scottsdale, and Columbus, OH), per the operator's own site. Hosts 180+ customers including 20+ carriers and two IXPs. Coordinate provenance (resolved 2026-09-12): Iron Mountain's own location page embeds a Google Maps link containing TWO coordinate pairs from two different Place IDs. This record uses 40.5210834,-74.3473835 — the pair the link anchors directly to the literal address string "3003 Woodbridge Ave, Edison, NJ 08837, USA" — which sits ~29 m from the independently-mapped OpenStreetMap building tagged "IO Datacenter" at the same address. The other page-stated pair (40.5216986,-74.3461546) carries no address string and lands ~145 m away; a naive extraction returns it, since the page labels neither. Both page-stated pairs are ~1.8-1.9 km from the US Census geocoder's point for this address, which interpolates along the street centre line and is wrong here.
Operator states 100% renewable energy matching plus on-site solar via '18,000+ rooftop solar panels' (7.2 MW on-site solar generation capacity) — described as the largest such installation of any North American data center, per Iron Mountain's own site.
Sources and provenance
- New Jersey Data Center | New Jersey Colocation · source retrieved 2026-09-21
- Iron Mountain Data Centers NJE-1 — 3003 Woodbridge Avenue · source retrieved 2026-09-12
- OpenStreetMap way/204316962 — IO Datacenter, 3003, Woodbridge Avenue · source retrieved 2026-09-12
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.