Jefferson Proving Ground Data Center
Undisclosed · Madison, IN · United States
Facility record
- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 38.82, -85.4
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-09-21
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Permitted
Jefferson County Board of Zoning Appeals denied an appeal and county commissioners upheld the zoning approval, allowing the project to move forward.
Underlying source
Source notes
Proposed hyperscale campus of nine buildings totaling ~7.2 million sq ft on 549 acres of the former Jefferson Proving Ground airfield, on land owned by the Ford family (Daniel Ford); the end-user/operator has not been publicly disclosed. Reported to draw hundreds of megawatts and be roughly 78% larger than Meta's Lebanon campus; projected 300-450 permanent jobs and ~$60M in annual county tax revenue. Coordinates are an approximate geocode of the former proving-ground airfield north of Madison. As of 2026-09-10, no official capacity, utility partner, or anchor-company figure has been released for this site. Independent, unofficial estimates cited in the same article range widely: one expert (Chien) says 9 GW 'is not unreasonable' for a power-dense AI training facility, while another (Inskeep) is 'very confident' it will need at least 1 GW. Neither is a project-stated figure, so no capacity is recorded. The site is 549 acres of the former Jefferson Proving Grounds Army base, ~8 miles north of Madison, IN.
Sources and provenance
- Commissioners uphold decision to allow a data center on 550 acres at Jefferson Proving Grounds · source retrieved 2026-08-05
- Zoning board allows controversial Madison data center project to move forward · source retrieved 2026-08-05
- Proposed JPG data center could generate $60M taxes annually · source retrieved 2026-09-21
- Questions persist about who will power the massive data center near Madison, Indiana · source retrieved 2026-08-05