KARIS DeKalb Campus (Peace and Gurler Roads)
Karis Acquisitions · DeKalb, IL · United States
Facility record
- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 41.892979, -88.724193
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-09-25
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Permitted
DeKalb City Council approved an amendment to Ordinance 2023-038 to accommodate a 1,750,000 sq ft data center in seven buildings at the NE corner of Peace and Gurler Roads; still carried on the city's project list as of 7/15/2026.
Underlying source
Source notes
Seven-building, 1,750,000 sq ft campus. Coordinates are the Peace Road / Gurler Road intersection (OSM); the approval describes the NE corner, so the true footprint lies north-east of this point. No megawatt figure appears in the city record.
Sources and provenance
- City of DeKalb Zoning & Development Projects list as of 7/15/2026 — Steven Goldin and Karis Acquisitions, NE Corner of Peace and Gurler Roads, 1,750,000 sq ft data center in seven buildings, approved 7/22/24 · source retrieved 2026-09-25
- City of DeKalb Zoning & Development Projects list as of 3/18/2026 (same entry) · source retrieved 2026-09-25