SOURCE-LINKED U.S. REGISTRY

Markley Group One Lowell Data Center

Markley Group · Lowell, MA · United States

Facility record

Lifecycle
OperationalSource-reported lifecycle
Location precision
approximate
Address as listed
2 Prince Ave
Coordinates
42.6334, -71.3162
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
50 MW
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Operational

    Markley Group One Lowell data center opens on site of former Prince Spaghetti factory; 352,000 sq ft, largest data center in Massachusetts

    Underlying source
  2. Operational

    Massachusetts DEP approves air permit for 8 additional diesel generators (27 total); residents appeal permit

    Underlying source
  3. Operational

    Lowell City Council passes one-year moratorium on data center construction and expansion; residents file first Massachusetts data center lawsuit

    Underlying source

Source notes

Coordinates are approximate city centroid (Sacred Heart/Back Central neighborhoods, Lowell). Facility serves 100+ customers including hospitals, universities, and police departments. Expansion includes land purchases by Markley near old power plant. Expansion plans stalled by moratorium. AI demand cited as driver of expansion since 2022. Delivered permanent-job counts are disputed - the abatement promised 100 jobs; the city and critics count ~26-30 full-time local workers while Markley cites ~100 total, with construction peaking ~120 (IBEW Local 103); recorded as unresolved (honest-zero). In September 2024, Markley executive vice president Jeff Flanagan said the company is committed to investing more than $350 million in the Lowell data center, of which more than $225 million had already been developed (The Sun of Lowell, via GovTech). The investment figure recorded here is that stated floor of $350 million. Massachusetts' 2024 sales-tax exemption is statutory eligibility, not a confirmed Markley award.

27 diesel generators (expanded from 7 original; 8 added in 2025 via DEP air permit); 16 cooling towers. Expansion moratorium passed by Lowell City Council April 2026.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory