Menlo Digital Richmond Virginia Data Center (Jamestown Drive)

Menlo Digital · Petersburg, VA · United States

Facility record

Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
2255 Jamestown Drive
Coordinates
37.199, -77.363
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
104 MW
Source record updated
2026-09-09

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Permitted

    Rezoned by Petersburg City Council in 2023 with subsequent approvals. A site plan has been submitted but not yet approved — comments and corrections on the most recent submission were returned in late April 2026 and an updated plan had not been resubmitted as of the reporting date.

    Underlying source

Source notes

Four-building campus totalling roughly 1.2 million sq ft on 74 acres, served by a planned 300 MW substation; the 104 MW figure is the reported supported IT load at full buildout, not the substation rating. Menlo's own site markets the project as 'Richmond Virginia Data Center'. Coordinates are an approximate geocode of the cited street address.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.