Meta Altoona Data Center Campus

Meta · Altoona, IA · United States

Facility record

Lifecycle
OperationalSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
41.6459, -93.4696
Serving utility, source-reported
MidAmerican Energy
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Operational

    Meta (Facebook) began building the Altoona campus in 2013; now its largest cloud campus at 5M+ sq ft after a seventh expansion; hosts GenAI/LLaMA compute

    Underlying source

Source notes

Operational since 2013; 5M+ sq ft after seven expansions — Meta's largest cloud campus. Meta's engineering blog documents Altoona as a GenAI infrastructure / LLaMA training site. INVESTMENT: 'more than $2.5 billion' is a cumulative multi-year figure across all expansions, recorded as the campus investment. Meta says more than 400 people work on-site in data center operations each day, and its info sheet lists "400+" operational jobs supported; the recorded permanent-job figure of 400 is that stated floor. As of October 2026, no cited source states the campus's operational capacity; ~350 MW per a third-party index is not recorded. Coordinates are the Altoona town centroid. Meta cites a cumulative capital investment of 'more than $2.5 billion' across seven Altoona expansions since 2013 (Data Center Frontier); the 2019 Building 5 phase was ~$400M (IEDA). Meta's Altoona info sheet lists '$2.5B+' as data center investment in Iowa. The recorded investment is the cumulative figure for the whole campus; the ~$400M figure covers the 2019 Building 5 phase alone and is not recorded.

Served by MidAmerican Energy; Meta matches load with long-term Iowa wind PPAs, including the 225 MW Great Pathfinder Wind project (Boone & Hamilton Counties, Apex Clean Energy, ~2022) tied to Altoona. MidAmerican delivered ~100% renewable to its Iowa customers in 2022. No on-site generation.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.