Meta Eagle Mountain Data Center Campus
Meta · Eagle Mountain, UT · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 40.3138, -111.9697
- Serving utility, source-reported
- Rocky Mountain Power (PacifiCorp)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-30
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
$750M initial campus announced
Underlying source - Operational
First building operational; campus expanded to 7 buildings totaling 4.5 million sq ft
Underlying source
Source notes
100% renewable match via Rocky Mountain Power's Schedule 34 green tariff, backed by dedicated solar PPAs — including the 525 MWac Faraday Solar project (Utah's largest, online Oct 2025), Appaloosa Solar (120 MW), and Graphite Solar (104 MW). Meta says its Utah projects add 1,719 MW of new renewables; buildings are LEED Gold.
Sources and provenance
- Meta Eagle Mountain Utah Campus — Baxtel · source retrieved 2026-07-05
- Can Utah become a data center hub without draining its water supply? — Great Salt Lake Collaborative / Salt Lake Tribune · source retrieved 2026-07-05
- Meta Eagle Mountain Data Center fact sheet · source retrieved 2026-07-06
- Can you build data centers in a desert without draining the water supply? — Grist · source retrieved 2026-07-06
- Meta announces mega expansion to Eagle Mountain data center project — Deseret News · source retrieved 2026-07-06
- Utah's largest solar plant set to power Eagle Mountain data center — Daily Herald · source retrieved 2026-07-06
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.