Meta Gallatin Data Center Campus

Meta · Gallatin, TN · United States

Facility record

Lifecycle
OperationalSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
36.3884, -86.4369
Serving utility, source-reported
TVA
Operational capacity, source-reported
300 MW
Planned capacity, source-reported
300 MW
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Meta announces Gallatin campus expansion

  2. Operational

    Campus officially launched November 2024 with six facilities on 900 acres

  3. Operational

    Gallatin Municipal Planning Commission grants permission for 135,000 sq ft tent-based GPU cluster facility; Meta building multi-billion-dollar GPU clusters in rapid deployment structures to accelerate AI capacity

    Underlying source

Source notes

Campus coordinates are city-centroid approximation for Gallatin, TN. Up to 12 data halls planned on 900+ acres per DPR Construction (general contractor). Meta is deploying AI GPU clusters in waterproof tent structures (rapid deployment structures) at this campus to accelerate capacity ahead of permanent building construction.

Third-party solar arrangement with TVA to match approximately 300 MW consumption; multiple PPAs including solar deals through TVA