SOURCE-LINKED U.S. REGISTRY

Meta Temple Data Center

Meta · Temple, TX · United States

Facility record

Lifecycle
OperationalSource-reported lifecycle
Location precision
approximate
Address as listed
3101 Industrial Blvd
Coordinates
31.1399225, -97.3812992
Serving utility, source-reported
Not established
Operational capacity, source-reported
152 MW
Planned capacity, source-reported
Not published
Source record updated
2026-08-26

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Under construction

    JE Dunn began construction of the three-building, 386-acre campus in April 2022.

    Underlying source
  2. Operational

    Meta brought the campus online as its first AI-optimised data center in the United States.

    Underlying source

Source notes

Three-building greenfield campus of more than 750,000 sq ft of data center and administrative space. JE Dunn lists the project status as completed. Meta reported $1.7m in direct funding to Bell County schools and nonprofits, including a $400,000 grant announced at the opening.

Meta says all energy use at the facility is matched with 100% clean and renewable energy; the company states its supported projects are adding 9,000 MW of new clean and renewable generation across Texas.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory